surface and environmental conditions:It should be free of dirty material such as dust, oil and paint
The surfaces such as extremely dry, hot and highly absorbent should be moisturized with water
The surfaces of the ceiling should be roughened before applying the plaster or undercoated with material to ensure attachment of the mortar
It should be paid attention that there is no air flow and circulation in the environment during application
The application temperature should be between +5 to +40 °C
packaging:
Polypropylene bags of 35 kg ( % ± 2 )
application:
Appropriate amount of plaster is prepared 5,0-5,5 liters of water/ 10 kg MAKONAT proportion in the plastering machine
Mortar is sprayed on the surface by machine
The application thickness is determined with the help of lath according to the smoothness of the surface
The mortar is flatted through surface finishingWhen the surface starts hardening, it is flatted with the help of a steel trowel
When a light presure is applied on the surface, if it does not subside, trifilling can be started
After trifiling process, polishing is made again with a steel trowel and surface is made ready for painting
storage:
At most 15 bags should be stockpiled one on another at a dry place
The bags must not be in contact with the floor and they must be protected from humidity and condensation
It must be used within 6 months after production date