surface and environmental conditions:
It should be free of dirty material such as dust, oil and paint
The surfaces such as extremely dry, hot and highly absorbent should be moisturized with water
The surfaces of the ceiling should be roughened before applying the plaster or undercoated with material to ensure attachment of the mortar
It should be paid attention that there is no air flow and air circulation in the environment during application
The application temperature should be between +5 to +40 °C.
packaging:
Polypropylene bags of 30 kg ( % ± 2 ).
application:
7 liters of clean water is down into mixture bowl; KARONAT plaster is added by sprinkling into the water
It is awaited for a period of approximately 2-3 minutes in order to cause the plaster to absorb the water
It is mixed with a hand mixer or with the aid of a trowel in order to obtain a homogenous mixture
The prepared mixture is poured into already prepared and lubed formwork
After pouring a layer, a layer of fiber or hemp is laid on that layer of plaster in order to make the mould more flexible and strong
Another layer of plaster is poured down of the laid fiber of hemp
The poured down into the mold will start to warm after a while, the plaster first warmed and then cooled will let itself to go after a while
The plaster taken out of the mould is left at the room temperature to dry before mounting.storage:
At most 20 bags should be stockpiled one on another at a dry place
The bags must not be in contact with the floor and they must be protected from humidity and condensation
It must be used within 6 months after production date